Rising To The Challenge: NASA Crane Project Takes SW Funk Industrial Contractors To New Heights

Bill Robinson
Bill Robinson

An aerial view of SW Funk Industrial Contractors placing an 84,000-pound prefabricated platform atop the existing gantry crane for NASA's Langley Research Center in Hampton, Virginia.

At the heart of NASA’s Langley Research Center in Hampton, Virginia, the Landing and Impact Research Facility (LandIR) — more famously known as “the gantry” — stands as one of the agency’s most iconic engineering structures: a towering 240-foot gantry crane stretching 400 feet long and 265 feet wide.

Completed in 1965 for the Apollo program, the facility trained 24 astronauts, including Neil Armstrong and Buzz Aldrin, who worked through the piloting challenges they would face during their descent to the Moon. It was designated a National Historic Landmark in 1985.

Today, the steel giant supports full-scale crash and impact testing for space and aviation, including a 20-foot-deep hydro-impact basin that can simulate water landings.

Joining Forces for a Landmark Upgrade

NASA recently called on SW Funk Industrial Contractors to complete a key upgrade to the gantry. Our team was tasked with installing a pre-built, 84,000-pound, 105-foot-long platform atop the crane’s center bent, which is more than 240 feet above the ground.

This was far from a routine lift. It was a feat of logistics, safety and structural precision that demanded months of preparation, custom equipment and seamless coordination between SW Funk Industrial Contractors, NASA and trusted partners like Guy M. Turner, the crane company.

A Mission in the Sky: Inside the Project 

A ground view of SW Funk Industrial Contractors preparing to place an 84,000-pound prefabricated platform atop the existing gantry crane for NASA's Langley Research Center in Hampton, Virginia.

NASA engineered and assembled a massive 84,000-pound prefabricated platform, but it was SW Funk Industrial Contractors who took on the high-stakes task of installing it 240 feet in the air — that’s equivalent to a 20-story building.

The platform needed to be installed atop the existing gantry crane, at a height beyond the reach of any standard manlift. The team’s responsibilities ranged from logistical planning and heavy rigging to executing safety-critical bolt connections on-site.

Key structural elements of the gantry affected by this installation included:

  • Upper longitudinal trusses
  • West, center and east bents
  • 150- and 220-foot platform levels
  • North and south diagonal braces
  • Elevator shaft access

To add another layer of complexity, two vital operations had to be completed before the large platform could make its descent. First, a smaller platform had to be built beneath where it would be placed. Then, several pieces of old NASA equipment, including antennas and weather monitors, had to be carefully dismantled and moved out of the way.

Expertise Meets Opportunity: Securing the Project

SW Funk Industrial Contractors was awarded the job following a competitive bidding process. Our success was rooted in deep technical knowledge and accurate cost projections. 

“We understood what this project demanded because of our background in steel erection,” says James Barnard, a Project Manager at SW Funk Industrial Contractors. “We partnered with Guy M. Turner, a crane company that deeply knows their stuff. That gave us the confidence to put together a very competitive, realistic and reasonable bid.”

Phase 1 of the project set the stage and involved detailed calculations to determine the type of crane needed, its precise placement and other critical factors. These determinations were formalized in our crane plan, which required NASA’s approval before work could proceed. 

Phase 2 brought the crane to life, with careful setup, testing and the integration of rigorous safety protocols. Finally, Phase 3 tackled the most formidable task: removing decades-old equipment and installing the massive platform. 

Each phase was executed with precision and efficiency, representing strong value within the project’s scope and complexity.

Advanced Planning: The Logistics Before Day One

James Barnard, Project Manager at SW Funk Industrial Contractors, studies a component for the NASA crane project before lifting begins.

According to Barnard, the sheer scale of the lift required an extensive pre-construction effort.

“We spent two months planning just the crane setup, including how to assemble it, where to place it and how to avoid interference with the existing structure,” Barnard explains. “You can’t just drop a crane of this magnitude anywhere. The footprint is massive, and there’s virtually no margin for error.”

To safely lift and install the platform, SW Funk Industrial Contractors brought in a massive crawler crane, capable of handling extreme vertical loads. The crane setup alone required two full weeks. This covered transport, assembly and the careful maneuvering of massive booms through the structure’s tight spaces. It wasn’t just about muscle — it was about math. 

“There’s a lot of technical calculation in a crane plan,“ Barnard says. “As a crane booms out and up, its lifting capacity decreases. Getting those numbers right, along with wind considerations and swing clearances, was critical to making this happen safely.”

The Top Priority at 260 Feet: Safety

With a platform this large and a working height exceeding the length of an Olympic swimming pool, safety planning on this project was non-negotiable and significantly more extensive than a standard job site. 

“There are no man baskets commercially available that can get our workers that high,” Barnard points out. “We had to bring in a secondary crane equipped with pre-engineered baskets to get workers up there safely.”

Fall protection, rigging redundancy and precise bolt hole placement protocols were implemented and reviewed repeatedly. Working with NASA, the SW Funk Industrial Contractors team developed contingency plans for nearly every scenario — from mid-lift wind gusts to emergency retrieval procedures. 

“We had to think through how our team would even hold onto the structure while bolting it into place,” Barnard continues. “It was a constant conversation between us and NASA about safety and doing things the right way.”

The Technical Challenge: One Swift Lift

Team members from SW Funk Industrial Contractors are climbing the NASA structure safely.

Typically, platforms like this are built piece by piece using stick-built construction, allowing for better control and less lifting strain. However, NASA opted to pre-assemble the platform on the ground, complete with its steel grading and structural attachments. This meant it all had to be lifted in one massive, 84,000-pound unit. 

“Lifting something that big, that high and keeping it stable — that’s not just difficult, it’s risky,” Barnard emphasizes. “We had to plan where to attach taglines, how long those lines needed to be and where our workers would stand to safely manage the sway and balance. It was incredibly complex.”

The platform would need to be positioned precisely on the center bent, while workers in a secondary crane’s man basket would need to work quickly to bolt up. Success would depend on perfect timing and seamless coordination.

Skybound: A Delicate Dance with the Weather

Because of the weather limitations of a crane this large, every movement to lift the platform had to be precisely timed.

“It's a 100-foot-long platform at 90,000 pounds, and it’s going up 250 feet in the air,” Barnard describes. “A crane of this magnitude has strict wind and weather restrictions that have to be accounted for.”

Fortunately, after two or three days of waiting through rain and high winds, the conditions cleared and the team could move forward. 

The lift itself took almost two hours to move from point A on the ground to point B at the top. However, once it was in place, the team couldn’t simply release it. The platform had to remain attached to the rigging and crane while the bolting process began. 

Out of 162 bolt holes, about half had to be secured before the crane could safely be released, ensuring the structure wouldn’t shift or fall. This process required constant coordination, further monitoring of the weather and close collaboration between the safety team and the crane crew.

In the end, the team’s careful planning paid off — the entire operation stayed right on schedule.

Crane Disassembly: Precision in Reverse

What’s remarkable about a crane of this size is that the complexity doesn’t end once the lift is done — dismantling it is just as intricate. Each section had to be removed in a precise sequence, carefully lowered and securely packed to maintain balance and safety.

The crew spent roughly six to seven days disassembling the crane, loading its components onto trucks and shipping them out. Each part was checked and accounted for before leaving the site, ensuring nothing was missed.

In the end, it was a fitting conclusion to a project that demanded just as much precision during disassembly as it had during the lift itself.

Reach for the Stars: The Future of the Project

A ground view of SW Funk Industrial Contractors placing an 84,000-pound prefabricated platform atop the existing gantry crane for NASA's Langley Research Center in Hampton, Virginia.

The crane gantry at NASA Langley is the last remaining structure of its kind, with others at international bases long retired. In many ways, this upgrade represents the preservation and modernization of a historical research tool.

Before installation, coordination with NASA, the CIA and the Air Force was necessary to remove legacy antennas and weather monitoring sensors from the top of the structure. This is a true testament to the broad collaboration required to bring this phase of the project to life. 

Future phases of the gantry upgrades will be bid out separately and SW Funk Industrial Contractors is eager to continue the partnership.

“We’ll be ready with feedback and lessons learned,” Barnard expresses. “It’s been a challenge, but that’s exactly what we specialize in.”

Let’s Build Something Extraordinary Together

SW Funk Industrial Contractors is proud to help preserve a piece of NASA history while preparing it for the next era of innovation. Stay tuned as we continue to reach new heights, one phase at a time.

Ready to take on your next challenge? Contact our team to learn how we can help you build with the same precision and vision.

Share this post