Against Rock, Ice & the Clock: How SW Funk Industrial Contractors Delivered Two Transformer Storage Pads

When a power generation facility needed backup transformer storage pads built at two sites (fast and in the dead of winter), they turned to SW Funk Industrial Contractors.
What followed was six months of rock-filled excavation, freezing temperatures, flooded pits and shifting schedules.
The goal? Two fully reinforced containment foundations ready for future transformer installations.
Here's how the project unfolded.
Years Ahead of Schedule. By Design.
Large utility transformers aren’t equipment you can order at short notice. Lead times can stretch for several years, which means the supporting infrastructure must be completed long before the transformers arrive on site.
The power generation facility needed backup transformer storage pads built across two sites, and each structure had to support the transformers’ weight while containing any potential oil leaks.
Because the units use mineral oil for cooling and lubrication, the foundations themselves serve as the first layer of environmental protection if a leak ever did occur.
SW Funk Industrial Contractors was contracted to build the containment structures from excavation through final steel installation.
Designed for Containment. Built for Access.
Each storage pad is a reinforced concrete containment basin built to handle more than just the weight of a transformer. A perimeter wall surrounds the pad, creating a three-foot-deep basin designed to capture any leaked fluid before it ever reaches the ground.
Inside, elevated concrete pedestals lift the transformers off the basin floor, keeping equipment accessible for maintenance while isolating it from anything that collects below. It's a simple detail with serious consequences if it's ever needed.
Steel access platforms, stairs and handrails were fabricated and installed so maintenance crews can safely clear the containment walls and reach every access point on the transformer.
Anchor bolts were also set during the concrete phase, so the moment the Hitachi units arrive for crane placement, the foundations are ready to go.
Two Open Fields. One Hidden Problem.

Most projects that SW Funk Industrial Contractors take on start inside active industrial facilities, but these didn't.
Both sites were open, undeveloped fields, which meant the first order of business was digging down 5.5 feet across a footprint of roughly 66 by 35 feet.
At one site, crews hit rock less than a foot below grade.
“The excavators were able to get through it, but it definitely slowed us down,” said Dan Clapp, Project Manager at SW Funk Industrial Contractors. “Then, disposing of the material was its own challenge. There's no shortage of people who want clean fill dirt, but not many want rocky mixed spoils.”
Nature Pushed Back. SW Funk Industrial Contractors Pushed Harder.
The project ran through the harshest stretch of winter, and both locations sat farther north and at higher elevations than SW Funk Industrial Contractors' typical work. The cold didn't let up, and neither did the issues it caused.
Snow and ice blanketed the sites for weeks. When temperatures finally rose, the melt had nowhere to go but straight down, turning the pits into collection basins.
“We had waterfalls basically coming into the excavation,” Clapp said. “We had to pump water and wait for things to dry out. It all added time to an already tight schedule.”
The elements may have been unpredictable, but the team's execution wasn't. They kept the project on budget and moving forward.
Small Crew. Big Output.

SW Funk Industrial Contractors maintained a core crew of around five, scaling up to 10 members during peak concrete and rebar phases before tapering off for steel installation and finishing work.
From the first excavation in late December through the final steel installation six months later, the team delivered:
- Two concrete containment structures
- Two transformer pedestal systems
- Two steel access platforms
Transformer manufacturing delays actually worked in the project's favor, adding schedule flexibility where the team needed it most.
"The steel wasn't on the critical path," Clapp explained. "As long as we were ready for the transformer delivery, we were in good shape."
In the end, no project delays were attributed to SW Funk Industrial Contractors.
Two New Pads. One New Partnership.
This power generation facility proved to be the ideal partner for a challenging project, bringing clear communication, realistic expectations around weather delays and a collaborative approach from the first dig to the final weld.
The ultimate measure of success came before the project was even fully wrapped: the client was already asking what else the team could do and was planning future projects with us.
"They were a great client to work for — very understanding and very fair," Clapp said.
The Job Gets Hard. We Get to Work.

The transformer storage pad project was a great example of what industrial construction actually looks like in the field: rock where there shouldn't be, water where it doesn't belong and temperatures that don't care about your schedule. Every challenge required a response, but none of them stopped the job.
In the end, the team delivered both transformer storage pads safely, on time and on budget, leaving a satisfied client already asking what’s next.