Heat Evaporation Foundations

The existing concrete tank foundation and pump pad had become compromised and needed to be replaced. This began with the demolition of the existing foundation. Once the foundation was demolished, 118 piles were driven and grouted prior to mobilization.  Once mobilized a mud mat was poured across the entire tank foundation as well as the pump pad work area.  The piles were cut to elevation, and tension plates were installed.  Concrete forms were set with #9 rebar before the 1.5T stainless embed ring was installed.  The embed ring was stabilized to remain horizontally and vertically within a 1/8-inch tolerance.  The concrete for the tank foundation was then placed successfully.

Throughout the entire project we remained on the clients schedule to ensure production was able to continue moving.

  • Westrock Covington
  • Covington, VA
  • Completed: 2021
  • Industry: Pulp & Paper
  • Scope: Steel Fabrication, Concrete